New construction licenses in the Paks II. project

12/16/20, 10:56 AM
The construction of more and more buildings can start in the Paks II. project. This time, the anti-corrosion work complex received the construction license.

More than a hundred structures are needed to implement the nuclear power plant units to be built. In the area of the Construction and Erection Base, which will be nearly 100,000 square meters, the construction of the first three CEB buildings is nearing completion. In addition, the work area has already been handed over to begin construction of the concrete mixing plant facilities. Now the complex of anti-corrosion works has received the construction license from the Hungarian Atomic Energy Authority.